Depending on the type of floor being installed and general conditions at the job site, the minimum average production rates for each man per day should be as follows:
If a loading dock is available, a 40-foot tractor trailer can be unloaded in two hours by two men using two pallet jacks. Moving the material to the area receiving the A/F installation depends on the distance from the loading dock and on having a clear path to move the material.
Where an outside hoist or Hi-Boy forklift is used because there is no loading dock, it may take four men four hours to unload a tractor trailer of material.
The size of a crew is affected by various factors that are unique to each project. Examples of these are: size of the area to be installed; availability of the work area in combination with other trades; distance of moving material from storage to area; having continuous flow of work without stoppages in project construction schedule. If these types of extraneous factors are not a consideration, then normal crew sizes for effective productivity rates in a given room area can be evaluated on the basis of the following square footages: